Project: Hazelwood Park Boardwalk Replacement (P-029)
Location: Hazelwood Park
The new boardwalk over the wetland along the CrossTown Trail is taking shape, and the hardest part is done. The work below the deck is finished, and construction is expected to wrap up around the turn of the year, weather permitting. Thank you for your patience as we build it right.
Where Things Stand: Your Questions Answered
What work is finished? All of the below-deck work is complete:
- Steel pin piles driven and cut to height
- Custom steel knife plates fabricated and in place
- Cross-bracing between piles in place
- Pile caps that will carry the framing installed
Why has it taken longer than planned? Building in a wetland isn’t like building on dry ground. The wetland’s soft peat soil can’t hold heavy machinery, so crews drove each pile with hand-held equipment. Each pile had to reach firm sand and gravel, which in several spots was deeper than expected. Where crews hit underground obstructions, piles were shifted a few inches from their planned locations.
Those few inches matter. The diagonal steel braces between piles are held by small “knife plates,” and each one must be set at the exact angle to meet the next pile. To protect the wetland, we keep on-site welding to a minimum. So the contractor measured every pile after it was in and had each plate custom-made in a shop. It took longer, but the fit is better and the wetland was disturbed far less.
We also adjusted parts of the design along the way to steer around tree roots. That let us keep trees that would otherwise have come down and protect the wooded character of the park. It added some time, but we think it was worth it.
What’s next? Work now moves above ground, where progress will be faster:
- Fastening steel connections and finishing the bracing
- Framing and installing composite decking and kick rail
- Building concrete footings where the boardwalk meets the trail
- Replanting disturbed areas with native wetland plants
Is the trail still closed? Yes, until construction is complete. The detour hasn’t changed: go around the site on nearby trails or the adjacent sidewalks.
What will the new boardwalk be like? The new boardwalk uses steel piles and composite decking in place of the aging timber. It will last longer and need much less upkeep, serving the CrossTown Trail for years to come.
Who can I contact with questions or concerns? For questions about this project, please email Parks & Trails Planner Brendan Hutchins or call 425-386-4110.
For more information about planned future construction projects, please visit the Capital Improvements page.
Recent News

New Winter Sports Classes

Construction Update | Hazelwood Park

Join the Community Activities Commission

Fall Recycling Collection | By the Numbers

Updated City Hall Lobby Hours

Explore the 2027 Preliminary Budget

Construction Alert | Pavement Overlay Program

Now Hiring: Maintenance Technician

Construction Alert | Hazelwood Park

Coming Soon: OpenGov for Permits and Inspections

City Hall Lobby Closures

Construction Alert | SE 76th Street

Newcastle’s New City Website Is Here

Now Hiring: Events & Recreation Coordinator